UTILITIES DISTRIBUTION SYSTEM - Extend Southeast Utilities - Phase 1
 
Project #: 0050401
 
Scope: Extension of the existing east campus utililties to support the future Campus Recreation and Wellness Center and provide pipe capacity to facilitate future "south" campus. The utilities include chilled water, domestic water, steam, and condensate.
 
Building: UTILITIES DISTRIBUTION SYSTEM
   
Project Status: CONSTRUCTION CLOSE
   
Construction Start: 5/16/2007
   
Construction Finish:
   
Facilities Management Phone:
  319-335-5500
   