Project Information
SUBSTATION L CONTROL BUILDING - |
|||
|
|||
Project #: |
0337801 |
||
Scope: |
Provide fault current analysis of Sub L, including connection to the "across campus tie" (ACT), as well as upgrade of its electro-mechanical relays to modern solid state relays in support of an upgrade/increase of the ACT capacity by other, U&EM projects. The study has indicated an overall switch gear upgrade/upsizing is required which will involve a second control building at Sub L. |
||
Building: |
Substation L Control Building |
||
Project Status: |
Substantial Completion |
||
Estimated Construction Cost: |
$999,900 |
||
Pre Bid Date: |
5/10/2012 |
||
Pre Bid Location: |
USB-302 |
||
Bid Date: |
5/24/2012 |
||
Bid Results: |
Bid Results | ||
Awarded To: |
Calacci Construction Co., Inc. |
||
Construction Start: |
7/5/2012 |
||
Construction Finish: |
12/14/2012 |
||