Project Information

CALVIN HALL -
Renovate West and South Entrances

 

Project #:

0357101    

Scope:

Renovate the west and south entrances.

Building:

Calvin Hall

Project Status:

Substantial Completion

Estimated Construction Cost:

$254,500

Pre Bid Date:

4/12/2012

Pre Bid Location:

311A CALH

Bid Date:

4/25/2012

Bid Results:

    Bid Results  

Awarded To:

City Construction Group LC

Construction Start:

5/4/2012

Construction Finish:

10/20/2012