Project Information
STUDIO ARTS - |
|||
|
|||
Project #: |
0369501 |
||
Scope: |
This project replaces the driveway pavement at Studio Arts parking lot to support Cambus traffic. |
||
Building: |
Studio Arts |
||
Project Status: |
Substantial Completion |
||
Estimated Construction Cost: |
$189,000 |
||
Pre Bid Date: |
5/1/2012 |
||
Pre Bid Location: |
USB 232 |
||
Bid Date: |
5/9/2012 |
||
Bid Results: |
Bid Results | ||
Awarded To: |
All American Concrete Inc. |
||
Construction Start: |
5/21/2012 |
||
Construction Finish: |
8/17/2012 |
||