Project Information
BOWEN SCIENCE BUILDING - |
|||
|
|||
Project #: |
0388101 |
||
Scope: |
Replace two 3000 GPM chilled water pumps in the basement of BSB. |
||
Building: |
Bowen Science Building |
||
Project Status: |
Accounting Close |
||
Estimated Construction Cost: |
$73,409 |
||
Pre Bid Date: |
1/4/2012 |
||
Pre Bid Location: |
MERF 1143 |
||
Bid Date: |
1/11/2012 |
||
Bid Results: |
Bid Results | ||
Awarded To: |
RM Boggs Co. Inc. |
||
Construction Start: |
1/18/2012 |
||
Construction Finish: |
4/6/2012 |
||