Project Information

BOWEN SCIENCE BUILDING -
Replace Chilled Water Pumps

 

Project #:

0388101    

Scope:

Replace two 3000 GPM chilled water pumps in the basement of BSB.

Building:

Bowen Science Building

Project Status:

Accounting Close

Estimated Construction Cost:

$73,409

Pre Bid Date:

1/4/2012

Pre Bid Location:

MERF 1143

Bid Date:

1/11/2012

Bid Results:

    Bid Results  

Awarded To:

RM Boggs Co. Inc.

Construction Start:

1/18/2012

Construction Finish:

4/6/2012