Project Information

Power Plant -
Relocate Utilities within Plant

 

Project #:

0647202    

Scope:

This project will relocate various piping within the Power Plant to allow foundation work (0647203) in support of new Boiler #12 (0647206).

Building:

Power Plant

Project Status:

Construction

Pre Bid Date:

4/18/2017

Pre Bid Location:

University Services Building (USB)-Room 202 @ 10:00 AM

Bid Date:

5/10/2017

Bid Results:

    Bid Results  

Awarded To:

American Piping Group, Inc.

Construction Start:

5/22/2017

Construction Finish:

10/20/2017