Project Information

Field House -
Install Ventilation System in Rooms 440 & 440A

 

Project #:

0655701    

Scope:

Installation of a rooftop mounted ventilation unit to provide exhaust and make-up air for laboratories 440 and 440A.

Building:

Field House

Project Status:

Accounting Close

Estimated Construction Cost:

$188,000

Pre Bid Date:

5/23/2017

Pre Bid Location:

Field House Room 440 (area where the project is being done)

Bid Date:

6/6/2017

Bid Results:

     

Awarded To:

Calacci Construction Company Inc

Construction Start:

2017-06-23

Construction Finish:

2017-10-12

 