Project Information

Power Plant -
Replace Boiler 11 Ash Valves and Upper Air Heater Tubes

 

Project #:

0692001    

Scope:

Replace Boiler 11 ash valves and upper portion of air heater tubes.

Building:

Power Plant

Project Status:

Substantial Completion

Estimated Construction Cost:

$539,500

Pre Bid Date:

5/4/2017

Pre Bid Location:

Power Plant Conference Room. Please use 207 West Burlington Street entrance.

Bid Date:

5/18/2017

Bid Results:

     

Awarded To:

Ragan Mechanical Inc

Construction Start:

2017-06-14

Construction Finish:

2017-10-23

 