The University of Iowa

Power Plant Flood Mitigation Measures

Project Number
0207302
Project Scope
This project will construct flood mitigation measures at the Power Plant approved by FEMA in PW1100v5.
Project Status
Archive
Square Footage
0
Estimated Cost of Construction
$1,748,800.00
Construction Start Date
October 2014
Substantial Completion Date
March 2015
Awarded To
Jasper Construction Services Incorporated
Architect(s)
Stanley Consultants Company