Project Number
0257013
Project Scope
Due to the heavy damage received in the June 2008 flood, FEMA and the University identified the replacement of HVC as the most responsible recovery/mitigation option. The project includes the replacement of Hancher.
Project Status
Finance & Operations
Square Footage
0
Estimated Cost of Construction
$4,336,247.00
Construction Start Date
October 2013
Substantial Completion Date
February 2016
Awarded To
Texas Scenic Company Inc