Seashore Hall

  • Utility trench work north of the PBSB electrical vault extending to the east side of SSH is underway. Mud sill placed, coordination of activities with Utility Distribution is on going

Psychological and Brain Sciences Building

  • Wall framing on all floors 90% complete
  • Mechanical ductwork rough-in occurring on all floors
  • Mechanical plumbing rough-in occurring on all floors
  • Electrical rough-in occurring on all floors
  • East stairwell step pans have been poured with concrete from B level to 4th floor
  • Exterior air vapor barrier is being applied as weather permits
  • Upcoming milestone: UI Utilities to install permanent high voltage switchgear in the next two to three weeks
Project Description

This project will construct a new facility to expand and relocate the Department of Psychological and Brain Sciences. The project also includes razing the southeast wing of Seashore Hall, allowing for construction of the new building, which will provide a direct connection to Spence Labs. The remainder of Seashore Hall will be taken down at a later date. 

The new building will be comprised of a mix of offices, dry laboratories, collaboration space, classrooms and student work areas. The Lower Level and Ground Level are composed of open commons spaces, classrooms and administration offices. The upper four stories contain faculty offices, dry laboratories, and open commons space.

Webcam
Project Number
0303801
Project Scope
This project will construct a new facility to relocate the Department of Psychological and Brain Sciences and raze the east wing of Seashore Hall.
Project Status
Construction
Square Footage
58,400
Project Cost
$23,779,000.00
Construction Start Date
October 2017
Substantial Completion Date
August 2019
Awarded To
Knutson Construction Services Midwest
Architect(s)
Berkebile Nelson Immenschuh McDowell