Clubhouse at Finkbine Golf Course and Support Facility - Construct New Building - Rebid

What's New

(updated October 2019)

Building structure is compete.  Exterior siding and painting ongoing.

Exterior utilities are 70% complete.

MEP is 75% complete.

Masonry 85% complete.

Grading and site work is 80% complete.  Concrete at exterior to be completed by November 1st.

Interior has been painted at both levels.  Tiling and finishes have commenced at the lower level.

Casework and trim packages are in fabrication.

Reviewing signage and kitchen packages.

Putting greens and associated golf course work is 85% complete.

Landscaping to commence in the spring.

Existing Clubhouse to be razed after new building is occupied in the spring.

Project Description

The Athletics Department intends to replace the existing Finkbine Golf Course Pro Shop with a new facility. The new facility will be approximately 19,000 gross square feet on two levels. The facility will include Men's & Women's Locker Rooms, an accessible retail pro shop, administrative offices, a full kitchen/ dining/ banquet event space. Accommodations to store and maintain the golf cart fleet, a storage area and golf driving range operations will be incorporated in the design. The new facility will provide proper weather shelter and safety for daily play customers and tournament participants.

Project Number
0633501
Project Scope
Construction of a new clubhouse. The building is intended to be emblematic and an instantly recognizable icon for Finkbine's renowned golf course and University of Iowa's golf program.
Project Status
Construction
Square Footage
19,000
Project Cost
$6,189,000.00
Construction Start Date
December 2018
Substantial Completion Date
February 2020
Awarded To
Conlon Construction Co
Architect(s)
BSB Design Inc