University of Iowa

Power Plant Procure and Install Boiler

Project Number
0647205
Project Scope
This project will supply and field erect new Boiler #12 inside the Main Power Plant.
Project Status
Construction
Square Footage
0
Project Cost
$4,551,123.00
Construction Start Date
April 2017
Substantial Completion Date
December 2018
Awarded To
Locke Equipment Sales Company