University of Iowa

University of Iowa Stanley Museum of Art Construct New Facility

What's New

Contractors mobilized to the site on August 26th installing the temporary sidewalk to re-route pedestrians around the site.

The major work occurring right now is the completion of the new electrical duct bank. UIU will be completing their task directly with pulling and terminating the new 15 Kv ductbank.

The new 20” water main work has been completed.

The contractors have started the first major milestone work with the drilling for the building caissons with an estimated duration of a month to month and and a half.

Webcam
Project Number
0657201
Project Scope
This project will construct a new museum of art facility on the main campus.
Project Status
Construction
Square Footage
60,400
Project Cost
$35,865,850.00
Construction Start Date
August 2019
Substantial Completion Date
October 2021
Awarded To
Russell Construction Co Inc
Architect(s)
Berkebile Nelson Immenschuh McDowell Incorporated