The University of Iowa

Chemistry Building Chemistry Building - Repair HVAC Ductwork Issues Phase 2

Project Number
0773601
Project Scope
This project will re-insulate the main supply duct work in the Chemistry Building's NW HVAC air handling system following the removal of duct lining in project 0754501 before the 2018 winter heating season.
Project Status
Archive
Square Footage
0
Project Budget
$159,500.00
Construction Start Date
February 2019
Substantial Completion Date
May 2019
Awarded To
Universal Climate Control Inc
Architect(s)
KFI Engineers