The University of Iowa

North Hall North Hall - Repair Water Infiltration Issues

Project Number
0777801
Project Scope
This project remediates water infiltration issues at North Hall, 20 W. Davenport Street on the East Campus.
Project Status
Archive
Square Footage
0
Project Budget
$176,900.00
Construction Start Date
August 2019
Substantial Completion Date
October 2019
Awarded To
Maxwell Construction Incorporated
Architect(s)
Shive Hattery Incorporated