Project Number
0798001
Project Scope
This project will replace the existing 208V/120V Main Distribution Panel (MDP1) in Van Allen Hall Room B16. Concurrently, the west half of Van Allen Hall fed by a 5KV electric service will be upgraded to 15KV as a separate project by ENGIE.
Project Status
Construction
Square Footage
0
Estimated Cost of Construction
$598,775.00
Construction Start Date
April 2022
Substantial Completion Date
July 2023
Awarded To
Trey Electric Corporation
Architect(s)
PRVN Consultants Incorporated