The University of Iowa

Utilities Distribution System Utilities Distribution System - Modify Steam Piping Near Pappajohn Business Building

Project Number
0811701
Project Scope
This project will eliminate the steam and condensate pipe expansion joint function of the Pappajohn steam vault, thus removing the need for further maintenance entry into this very cramped area with limited access.
Project Status
Archive
Square Footage
0
Project Budget
$59,650.00
Construction Start Date
September 2019
Substantial Completion Date
November 2019
Awarded To
American Piping Group Inc
Architect(s)
Shive Hattery Incorporated