The University of Iowa

UIHC John W. Colloton Pavilion - Modify Chilled Water Infrastructure

Project Number
0824101
Project Scope
The project will modify and install controls and measurement devices at the existing mechanical equipment and chilled water infrastructure located in John W. Colloton Pavilion.
Project Status
Construction
Square Footage
0
Project Cost
$471,750.00
Construction Start Date
December 2020
Substantial Completion Date
March 2021
Awarded To
Day Mechanical Systems Inc
Architect(s)
IMEG Corp