The University of Iowa

Hospital Parking Ramp No. 4 2021 Ramp Maintenance

Project Number
0872901
Project Scope
This project will install penetrating sealer, waterproofing membrane, and miscellaneous repairs to Hospital Ramp No. 4 in accordance with the 2019-2023 Ramp Maintenance Plan.
Project Status
Substantial Completion
Square Footage
0
Project Cost
$397,420.00
Construction Start Date
February 2021
Substantial Completion Date
September 2021
Awarded To
Western Specialty Contractors
Architect(s)
Shive Hattery Incorporated