The University of Iowa

Carver Biomedical Research Building Replace Lab Exhaust System

Project Number
0874401
Project Scope
This project will replace the eight existing exhaust fans/stacks serving the labs in CBRB as well as establish new, dedicated exhaust fans for the BSL3 lab.
Project Status
Substantial Completion
Square Footage
136,442
Project Budget
$1,940,000.00
Construction Start Date
July 2021
Substantial Completion Date
December 2021
Awarded To
Tricon General Construction Incorporated
Architect(s)
Design Engineers PC