Chemistry Building Replace AHU Steam Coils

Project Number
0874601
Project Scope
Replace fifth floor AHU and NW AHU steam heating coils.
Project Status
Accounting Close
Square Footage
0
Estimated Cost of Construction
$827,000.00
Construction Start Date
May 2021
Substantial Completion Date
July 2022
Awarded To
Bowker Mechanical Contractors LLC
Architect(s)