The University of Iowa

Bowen Science Building Reconfigure 1-300 Core Lab Exhaust

Project Number
0902001
Project Scope
This project will reconfigure the Core 1-300 lab exhaust.
Project Status
Construction
Square Footage
0
Estimated Cost of Construction
$341,000.00
Construction Start Date
March 2022
Substantial Completion Date
June 2022
Awarded To
Baker Group
Architect(s)
Design Engineers PC