Mayflower Hall Mayflower Hall - Install Reheats to the HVAC on Main Floor

What's New

Project will install reheats to VAV's on level 1 of Mayflower Hall community spaces to provide supplemental heating ability when building is in cooling mode. Construction to take place summer 2022. 

Project Number
0904901
Project Scope
Project will install reheats to VAV's on lobby and office areas on level 1 of Mayflower Hall
Project Status
Archive
Square Footage
0
Project Budget
$168,900.00
Construction Start Date
February 2022
Substantial Completion Date
July 2022
Awarded To
Prime Mechanical Inc
Architect(s)
Design Engineers PC