State Hygienic Laboratory at the University of Iowa - Construct New BSL3 with Additional Support Space

Project number
0920001
Project building
Project scope
This project will use the CM@R delivery method to construct a totally new BSL#3 lab addition to the State Hygienic Lab on the Oakdale Campus. This addition, positioned on the SE corner of the existing building, will contain not only the new BSL3 on the second level but also new support spaces on the ground level as well as the second level with the new lab. A new penthouse on the second story roof will supply the new lab.
Project status
Substantial Completion
Project Budget
$9,421,741.00
Bid date
Construction start date
Substantial completion date
Awarded to
Carl A Nelson & Company
Architect(s)
RDG Planning And Design