Project Number
0925901
Project Scope
This project will install penetrating sealer, waterproofing membrane, and miscellaneous repairs to Hospital Ramp No. 3 and Hospital Ramp No. 1 in accordance with the 2019-2023 Ramp Maintenance Plan.
Project Status
Construction Close
Square Footage
0
Estimated Cost of Construction
$1,016,740.00
Construction Start Date
March 2022
Substantial Completion Date
August 2022
Awarded To
Pullman SST Inc
Architect(s)
Shive Hattery Incorporated