Project Scope
This project will redesign the parking lot area to address current safety and maintenance issues. This includes modifications and removal to existing parking lot islands, reconstructions of ADA parking and the entry path into the building, and upgrades to the parking lot lighting.
Project Status
Construction
Square Footage
0
Estimated Cost of Construction
$122,700.00
Construction Start Date
September 2022
Substantial Completion Date
December 2022
Awarded To
McComas Lacina Construction Company Incorporated
Architect(s)
Shive Hattery Incorporated