Project Number
0968301
Project Scope
This project will remodel the first floor of PSRB for temporary use by HHP. Includes finish repairs and upgrades and two eyewash stations. Furniture will be re-used from South Quad, 2nd floor and whatever HHP would like to re-use from their spaces in field house.
Project Status
Construction
Square Footage
0
Estimated Cost of Construction
$206,365.00
Construction Start Date
December 2022
Substantial Completion Date
April 2023
Awarded To
RoCon Construction LLC
Architect(s)
OPN Architects