Project Scope
The Scope of Work at these facilities includes concrete repairs such as spalling, cracks, painting steel girders & pedestrian bridge metal floor deck, expansion joint repairs, sealant replacement, waterproofing membrane installation (full system & overlay), cable barriers, flushing of drains, handrail repairs, stair pan repairs, pavement markings, Post-Tension grout pocket repairs, penetrating sealer application, and other miscellaneous work items.
Project Status
Construction
Square Footage
0
Estimated Cost of Construction
$644,537.00
Construction Start Date
February 2023
Substantial Completion Date
July 2023
Awarded To
Western Specialty Contractors
Architect(s)
Shive Hattery Incorporated