Iowa Advanced Technology Laboratories - Install HEPA Filtration System to Room 290

Project number
1008501
Project scope
This project will turn Room 290 into a Class 10,000 clean room. Basic requirements include installation of the following owner-provided equipment: (12) Fan powered HEPA units, (4) 3’x3’ Sidewall return ducts, (13) 2’x4’ Clean room LED light fixtures, Clean room ceiling tile and grid (320 gasket style). Contractor provided and installation of: (12) Single pole switches (individual power per HEPA unit), 120V Circuit and power connections to FFU HEPA diffusers, Temperature controls, and HVAC insula
Project status
Construction
Project Budget
$65,650.00
Construction start date
Substantial completion date
Awarded to
Climate Engineers Incorporated