The University of Iowa

West Campus Transportation Center West Campus Transportation Center - Replace Circulation Piping on Mezzanine Level and Restore Building Envelope

Project Number
1030601
Project Scope
This project will replace the circulation pipe on the mezzanine level of the West Campus Transportation Center to the electric heater.
Project Status
Construction
Square Footage
0
Project Budget
$59,127.00
Construction Start Date
August 2023
Substantial Completion Date
September 2023
Awarded To
RMB Company Inc
Architect(s)
Brooks Borg And Skiles