Project Scope
This project will replace the circulation pipe on the mezzanine level of the West Campus Transportation Center to the electric heater.
Project Status
Construction
Square Footage
0
Project Budget
$59,127.00
Construction Start Date
August 2023
Substantial Completion Date
September 2023
Awarded To
RMB Company Inc
Architect(s)
Brooks Borg And Skiles