Project Number
0939701
Project Scope
This project will replace the imaging equipment in Main Operating Room #8 with a Pheno Robot X-ray and includes updates to finishes, lighting, flooring and casework.
Project Status
Substantial Completion
Square Footage
0
Project Budget
$699,000.00
Construction Start Date
December 2022
Substantial Completion Date
September 2023
Awarded To
Knutson Construction Services Midwest Inc
Architect(s)
The S/L/A/M Collaborative Inc