Project Number
1019801
Project Scope
This project will replace the synthetic turf at Stew and Lenore Hansen Football Performance Center.
Project Status
Construction
Square Footage
84,200
Estimated Cost of Construction
$85,000.00
Construction Start Date
February 2023
Substantial Completion Date
May 2023
Awarded To
FieldTurf USA Inc
Architect(s)
Shive Hattery Incorporated