The University of Iowa

English-Philosophy Building Add Redundancy for Chilled Water Pump

Project Number
0901601
Project Scope
This project will add a second CW pump to the building cooling system for redundancy/reliability.
Project Status
Design
Square Footage
0
Estimated Cost of Construction
$190,000.00
Substantial Completion Date
April 2023
Architect(s)
PRVN Consultants Incorporated