The University of Iowa

Slater Hall Slater Hall - Replace Roof

Project Number
0929101
Project Scope
This project will replace the upper main roof of Slater Residence Hall.
Project Status
Substantial Completion
Square Footage
0
Project Budget
$435,135.00
Construction Start Date
June 2022
Substantial Completion Date
July 2023
Awarded To
Dryspace Incorporated
Architect(s)
Shive Hattery Incorporated